Rebuilding After a Wildfire in Malibu: What Homeowners Should Know
2026-11-25
Few places show how quickly a landscape can change like Malibu. The Woolsey Fire, which started on November 8, 2018, destroyed more than 450 homes in the City of Malibu, including houses along Kanan Dume Road. The Franklin Fire followed in December 2024, and the Palisades Fire in January 2025 destroyed 720 structures within city limits, according to the City. Our Malibu Residence is rising on Kanan Dume Road, on the site of a home lost in the Woolsey Fire. This guide shares what we have learned about rebuilding, from the first planning meeting to building for the next fire season.
Why rebuilding takes time
Rebuilding here is rarely quick. By late 2025, roughly half of the homes lost in the Woolsey Fire had been rebuilt, and ten months after the Palisades Fire the City had issued 11 rebuild permits. By June 2026 it had issued its 100th Palisades rebuild permit and the first certificate of occupancy for a completed home. Much of that time goes into the steps below, so understanding them early pays off.
1. Confirm who reviews your property, and what was legally permitted
Along the Malibu coast, some properties sit inside the City of Malibu and others in unincorporated Los Angeles County, each with its own planning department, code amendments and fee programs. The first step is confirming which agency reviews your lot.
The second step is your permit history. The City of Malibu recommends checking which structures on the lot were legally permitted, because its simplest rebuild options start from the home as it was approved and permitted at the time of the fire. Anything that was never permitted is not part of that baseline.
2. Choose your rebuild path
In the City of Malibu, fire rebuilds are organized around three broad options:
- Like-for-like. Rebuilding the home as it was approved and permitted at the time of the fire, in the same location.
- Like-for-like plus 10%. The same home in the same location, with up to 10% more square footage and/or height. The added area has to meet current development standards and cannot expand existing nonconformities.
- A larger or relocated home. Anything more than 10% larger, or in a new location on the lot, goes through a fuller planning application and review.
The first two options are processed through an administrative Planning Verification, which the City's own planners describe as the easiest way to secure a building permit.
The City also waives its rebuild fees for these two options when the home was the owner's primary residence at the time of the fire. For Woolsey Fire rebuilds that program is closing: applications were due by June 30, 2026, and no fees will be waived after December 30, 2026. For the Broad, Franklin and Palisades fires, the City Council approved a separate program in July 2025 with stricter rules, including a notarized affidavit recorded against the property and a full refund of waived fees if the property is sold before the rebuild is finished. Its deadlines run to June 30, 2028 for applications and planning approvals, and December 30, 2030 for building permits.
3. Understand the coastal permit exemptions
The entire City of Malibu lies within the California coastal zone, so development normally needs a Coastal Development Permit. Section 30610(g) of the Coastal Act exempts the replacement of a legally existing structure destroyed by a disaster, as long as it is in the same location, conforms to current zoning and does not exceed the floor area, height or bulk of the original by more than 10%.
After the January 2025 fires, Executive Order N-4-25, signed by Governor Newsom on January 12, 2025, suspended CEQA and Coastal Act permitting for qualifying rebuilds in substantially the same location and within 110% of the original footprint and height. In April 2025 the Coastal Commission also approved changes to Malibu's Local Coastal Program to streamline rebuilding after the recent fires and future disasters. These routes have different conditions, and the executive orders cover the January 2025 fires, not Woolsey rebuilds, so confirm which one applies to your lot before the design is fixed.
4. Planning first, then building
In Malibu, permitting happens in two steps. Planning reviews zoning: where the house sits, its square footage and its height. Building Safety then reviews the construction documents against the building code, including materials and methods. Along the way, a rebuild usually needs sign-off from other reviewers, such as Public Works, Environmental Health for the onsite wastewater system, geology, biology, the Fire Department and Los Angeles County Waterworks.
This is where coordinated documentation saves months. Every reviewer reads the same set, so drawings in which architecture, structure and site work agree mean fewer rounds of comments. That is why we produce construction documents from one coordinated BIM model: a change made for one reviewer carries through to every sheet.
5. Build for the next fire
A rebuilt home has to meet today's wildfire construction standards, not the ones in force when the original house was built. California's requirements for exterior wildfire exposure were long found in Chapter 7A of the Building Code; since January 1, 2026 they are part of the 2025 California Wildland-Urban Interface Code (Title 24, Part 7). They cover roofing assemblies, flame- and ember-resistant vents listed by the State Fire Marshal, ignition-resistant exterior materials and vegetation management, which must be in compliance before a permit receives final approval.
Beyond the code minimum, design choices matter: simple roof forms with fewer places for embers to collect, enclosed eaves, non-combustible surfaces close to the house, and a landscape plan that keeps fuel away from the walls.
6. Designing within the limits: our Malibu Residence
The Malibu Residence had to stay within its original footprint, with only a 10% expansion. Rather than treating that as a constraint, the design focuses on precision and restraint: two clearly organized areas, generous glazing toward the views, and a light-gauge steel structure with no traditional wood studs or interior load-bearing walls. Phase 1 is now about 78% complete, with the envelope, glazing, stairs, railings and interior wood finishes largely in place.
Before you start
Every fire rebuild is different, and the rules have changed more than once since 2018. Treat this article as general information and confirm the current requirements with the City of Malibu or Los Angeles County before you commit to a design. If you are planning a rebuild in Malibu or the Santa Monica Mountains, we would be glad to talk it through: get in touch.