Malibu Residence
Phase 1 · 78% complete
Where we are
A rebuild after the Woolsey Fire, now in the transition from construction shell to finished residence.
Malibu Residence, a single-family home in Malibu, California, is approximately 78% complete for Phase 1, a major milestone in its rebuild after the Woolsey Fire. Required to stay within the original footprint with only a +10% expansion, the design focuses on precision and restraint. The exterior envelope, glazing, stair elements, railings and interior wood finishes are largely in place, with current work focused on façade detailing, final finishes and the transition from construction shell to finished residence.
How it got here
February 2023
Site preparation
Clearing the lot and starting earthwork on the hillside.


June - August 2023
Excavation and grading
Excavating and compacting the pad for the lower level, and placing underground systems.



September 2023
Foundations
Footings formed and reinforced across the building footprint.


October 2023
Slab pour
The slab is poured and finished, and framing materials arrive on site.



November - December 2023
Lower-level walls
Formwork and reinforcement for the concrete walls of the lower level.


May 2024
Concrete structure
The concrete lower level is complete and the steel framing members are delivered.



September 2024
Steel frame
The light-gauge steel post-and-beam frame rises across the site.



April - May 2025
Closing in
Sheathing, roofing and openings close in the house.



April 2026
Façade and glazing
Stucco façade, large glazing and balcony railings in place; the scaffolding starts to come down.



April 2026
Interior finishes
Wood wall paneling and stone counters go in.



July 2026
Interiors take shape
Bar, lighting and the first furniture in place.



July 2026
Phase 2 begins
Grading around the house and the first boulders on site for the landscape.